PROJECT: YAMAL LNG
SCOPE OF WORK: Supply and installation of ventilation systems
CUSTOMER: JSC Renaissance Construction
LNG PLANT FACILITIES: Power Plant, BOG-1, Car Gate, Truck Gate, Chemical Warehouse, Central Security Building
EXECUTION PERIOD: September 2016 – December 2017
STATUS: Facilities commissioned
PROJECT: Construction and Installation Base for the first stage of the Rooppur NPP
SCOPE OF WORK: Supply, installation, start-up and adjustment works, and commissioning of intra-building ventilation and air conditioning systems
CUSTOMER: JSC “Institute Orgenergostroy”
EXECUTION PERIOD: 2017
STATUS: Facility commissioned
PROJECT: VTB Arena — Lev Yashin Central Dynamo Stadium
SCOPE OF WORK: Supply, installation, testing, and commissioning of engineering systems for the underground part of Section 2 of the Multifunctional Center (MC) and the complex consisting of the VGK Multifunctional Public Complex and the Multifunctional Center (Stage 2)
CUSTOMER: JSC “RMO-GROUP”
EXECUTION PERIOD: 2017 – 2019
STATUS: Facility commissioned
PROJECT: Center for High-Precision Metalworking
SCOPE OF WORK: Installation of ventilation systems in Building 153
CUSTOMER: JSC “RPC Istok named after A.I. Shokin” (RPC – Research and Production Company)
EXECUTION PERIOD: 2019
STATUS: Facility commissioned
PROJECT: Construction of a Nuclear Research Facility Based on the Multipurpose Fast Neutron Research Reactor MBIR
SCOPE OF WORK: Supply of equipment. Execution of construction and installation works at the facility.
CUSTOMER: JSC “Institute Orgenergostroy”
EXECUTION PERIOD: 2020 – present
STATUS: Facility under construction
PROJECT: Novovoronezh NPP‑2 – Works on the construction of the start-up complex for the first power unit
SCOPE OF WORK: Execution of design works; development, manufacturing, supply, and installation of heating, ventilation, and air conditioning systems at the following facilities: Reactor Building (10 UJA), Radioactive Waste Processing and Storage Building (00 UKS), Turbine Building (10 UMA), Ventilation Systems for Electrical Rooms (10 UKS, 10 UBP, 10 UBD), Auxiliary Reactor Building (10 UKS)
CUSTOMER: JSC “UEC” (JSC “United Energy Construction Corporation”)
EXECUTION PERIOD: 2010 – 2017
STATUS: Commissioned